| Schedule Expended (actual/planned) | 0/90 | 0% /100 % |
| Resources Expended (actual/planned) | 0/0 | 0 % / 0% |
| Resources Available / Resources Required | 0/0 | 100% |
| Deliverables Delivered (actual/planned) | 1 / 1 | 100% / 100% |
The project was re-thought and re-resourced on July 6th to run to the
same finishing date of November 30th 1998: 90 JRC working days. Re-planning
and re-scheduling is incomplete as yet because requirements, architecture
and resources are not yet known: only the schedule is known. Project
was originally initiated with full management support by A. Annoni on April
10th, 1998 and was to run until November 30th 1998: 160 JRC working days.
Go to Project Home Page
Updated 6 July1998